Clean the mould, fit it properly and apply oil
¨
Fill the concrete in 3 equal layers
¨
Tamp each layer with 35 strokes by tamping rod
¨
Strokes of above layer should penetrate the bottom
layer
¨
Give additional strokes from sides to remove the air
bubbles
¨
Level the cube with trowel
¨
After 3 – 4 hours, do smooth finish
¨
Mark the identification (see list)
¨
Note down the cube details for records
¨
Cover the specimen after 5 hours with wet gunny bags
¨
Demould the
cube after 24 hours
¨
Keep the cube in the curing tank immediately
Frequency of cube casting for each grade of concrete